How to write a SWMS: step by step, with a roof job example

When a Safe Work Method Statement is required, what goes in it, how to write one step by step, and a worked example for roof work over 2 metres.

A roof plumber kneeling on new corrugated iron sheets behind edge protection on a two-storey house, back to the camera, early morning light

Here's how to write a SWMS: name the high risk construction work on the job, break the job into the steps you'll actually do, list the hazards in each step, set controls for each hazard starting from the top of the hierarchy of control, and name who makes sure each control is in place. Then go through it with the crew, keep it on site and work to it.

A Safe Work Method Statement (SWMS) is a written document that sets out the high risk construction work on a job, the hazards and risks that work creates, and how those risks will be controlled, monitored and reviewed. It isn't a test of how much paper you can produce. Two clear pages your crew has read beat forty pages sitting in the glovebox.

What is a SWMS?

A SWMS, or Safe Work Method Statement, is the document Australian work health and safety law requires before high risk construction work starts. It names the high risk work, the hazards and risks that come with it, the controls you'll use, and how those controls are put in place, checked and reviewed. It's written for the people doing the work, so it has to fit the job and be easy to follow.

Safe Work Australia's model Code of Practice: Construction Work (November 2024) says its main purpose is to help the business, supervisors and workers put the controls in place and keep an eye on them. That's the test. A SWMS is a working document for the crew, not a form you hand the builder and forget about.

It's also separate from a job safety analysis or a general risk assessment. You can keep using those. They don't stand in for a SWMS when the law asks for one.

When is a SWMS legally required?

A SWMS is legally required before any construction work that falls into one of the 18 categories of high risk construction work in regulation 291 of the model WHS Regulations. Every state and territory except Victoria uses those regulations, and Victoria's own regulations list 19 categories. If a job hits none of them, you don't need a SWMS, but you still have to manage the risks.

High risk construction workTrade example
Risk of a person falling more than 2 metresRoof sheeting, roof trusses, an evaporative cooler on a roof
On a telecommunication towerFitting equipment to a tower
Demolition of a load-bearing or structural elementTaking out a load-bearing wall in a reno
Likely to disturb asbestosDrilling into an asbestos cement wall, lifting old floor tiles
Structural alterations or repairs needing temporary supportPropping a ceiling before a wall comes out
In or near a confined spaceWorking inside a large sewer pit
In or near a shaft or trench deeper than 1.5 metres, or a tunnelLaying pipe in a 1.8 metre trench
Using explosivesBlasting rock (explosive power tools don't count)
On or near pressurised gas mains or pipingDigging footings beside a gas main
On or near chemical, fuel or refrigerant linesPlant room work around refrigerant lines
On or near energised electrical installations or servicesDrilling into a wall with live wiring, work near overhead power lines
In an area that may have a contaminated or flammable atmosphereRemoving a tank that held fuel
Tilt-up or precast concreteStanding tilt panels
On or next to a road, railway or other traffic corridor in useDriveway and kerb work beside a live road
Where powered mobile plant is movingAn excavator or skid steer working on site
In an area with artificial extremes of temperatureCool room or freezer fit-out
In or near water or other liquid with a risk of drowningWork beside a pool, dam or river
Diving workUnderwater inspection or repair

"Near" means close enough that you could hit or puncture the service. Under the Code, power leads and power tools don't make a job electrical high risk work. Read the list with the site in mind, not only the task. A simple job can hit three categories at once.

Who has to write the SWMS?

The business doing the high risk work prepares the SWMS, or makes sure one is prepared, before the work starts. If you're a sole trader or a subbie doing the work, that's you. You must consult the workers who'll do the job while you write it. On a construction project, give the principal contractor a copy before you start.

Under the WHS Regulations, a construction project is construction work costing $250,000 or more. That's where a principal contractor comes in, and the builder will usually want your SWMS before you get through the gate. A smaller domestic job often has no principal contractor, but the SWMS is still yours to prepare and follow.

When two businesses do high risk work side by side, say a roof plumber fixing sheets and a crane crew lifting them, each needs a SWMS for its own work. You can write one between you or two separate ones, as long as the controls don't clash.

What goes in a SWMS?

A SWMS must identify the high risk construction work, the hazards and risks to health and safety from it, the controls for those risks, and how the controls will be put in place, monitored and reviewed. Most also carry the job details, who's responsible, which workers were consulted and a sign-on. Every control should read as an instruction, never a judgement call.

Here's a layout that covers it:

  • Business name, ABN and the person responsible for making sure the SWMS is followed
  • Site address, a short job description and the principal contractor, if there is one
  • The high risk construction work categories that apply
  • The job broken into steps, in the order you'll do them
  • Hazards and risks for each step
  • Controls for each hazard, highest level first
  • Who checks each control is in place
  • PPE, plant and equipment, and the licences and tickets the work needs
  • Workers consulted, and a sign-on for everyone doing the work
  • The date it was prepared, and a review date if you set one

The Code gives "use appropriate PPE" as an example of a line that doesn't detail the control. Write "P2 respirator and safety glasses while cutting fibre cement" instead. The person reading it on site shouldn't have to decide what you meant.

How do you write a SWMS, step by step?

Write a SWMS by walking through the job in the order you'll do it. Split it into steps, find what can hurt someone at each step, choose controls from the top of the hierarchy down, and name who's responsible for each hazard. Then go through it with the crew, fix whatever they pick up, and get everyone to sign on before work starts.

Writing the SWMS

  1. Check which high risk work applies.

    Go down the 18 categories with this site in mind. Overhead power lines, a nearby trench or a bobcat on site can each add a category.

  2. Break the job into steps.

    Set-up, access, the work itself and clean-up. Use the order you'll really work in, so the crew can follow it on the day.

  3. List the hazards in each step.

    Falls, falling objects, live services, asbestos, manual handling, heat and plant. Look at the site, or good photos of it, before you write.

  4. Pick controls from the top down.

    Get rid of the hazard if you can. If not, substitute, isolate or engineer it out, then add procedures, and only then PPE.

  5. Name who's responsible.

    For each hazard, the person who makes sure the controls are in place before work starts and stay in place while it runs.

  6. Go through it with the crew.

    They know the job and the site. Change the SWMS for anything they spot, then have each worker sign on.

The hierarchy of control in plain English

The WHS Regulations make you work down the hierarchy of control for certain risks, and it's the right way to think about all of them. The higher up the list a control sits, the less it relies on someone getting it right every time.

LevelWhat it meansOn a roof job
EliminateRemove the hazardAssemble the cooler frame on the ground, not on the roof
SubstituteSwap for something less riskyShorter sheet lengths two people can carry safely
IsolateKeep people away from itBarricade the ground under the roof edge
EngineeringPhysical controlsEdge protection, a scaffold, a materials hoist
AdministrativeProcedures, training, signsNo sheet handling in strong wind, a spotter for plant
PPEThe last lineFall-arrest gear, hard hats for anyone below, sun protection

A SWMS that relies on fall-arrest gear alone at an open roof edge will get questioned by any builder or inspector, and fair enough. Put the edge protection in first.

A worked example: replacing roof sheets on a two-storey house

Here's a SWMS for a common job: replacing corrugated iron roof sheets on a two-storey house, eaves about 6 metres up, with the overhead service line running to the front of the house. Two categories apply: a risk of falling more than 2 metres, and work near energised electrical services. Swap in your own site and crew.

Job: replace roof sheeting, flashings reused. High risk construction work: fall of more than 2 metres, and work near an energised overhead service line.

StepHazardsControlsWho
1. Set-upObjects falling on people below, the public walking pastBarricade and signs under the work area. Materials stacked clear of the edgeLeading hand
2. AccessFalls from the scaffold or ladderScaffold with stair access, erected and tagged by a licensed scaffolder. Ladders secured top and bottomLeading hand
3. Edge protectionFalls from the roof edgeGuardrail around the perimeter, checked before anyone steps onto the roofLeading hand
4. Service lineContact with live overhead conductorsOwner contacts the network operator before the job to have the line isolated or covered. Keep your state's approach distances. No sheets lifted near the line until that's doneOwner
5. Old sheets offFalls through skylights or brittle sheeting, cuts, sheets caught by wind, asbestos in older roofsMesh or covers over skylights. Roof checked for asbestos before work starts. Cut-resistant gloves. Stop handling sheets when wind makes them hard to holdLeading hand
6. New sheets upManual handling, dropped sheetsMaterials hoist to the roof, two-person carries, sheets tied down on the roofEach worker
7. FixingPower tool injuries, heat stress, UVGuards on tools, early start, water and shade breaks, long sleeves, hat and sunscreenEach worker
8. Clean-upOff-cuts and screws falling from the roofOff-cuts bagged on the roof and lowered, never thrownEach worker

Licences and tickets: everyone on site holds a general construction induction card (white card). Where a person or object could fall more than 4 metres from the scaffold, it's erected by someone with a scaffolding high risk work licence.

PPE: safety boots, cut-resistant gloves while handling sheets, hard hats for anyone working below, sun protection, and fall-arrest gear for any edge work outside the guardrail.

Look at the controls column. Each one is something a person can check with their eyes on the day. Nobody on the roof has to work out what "appropriate" means.

Price this into the job too. Scaffold, edge protection and a hoist are real costs, and they belong on the quote as line items, not in your margin. Our guide on how to quote a job covers setting out a quote so the customer can see what they're paying for.

Do you need to keep the SWMS on site?

Yes. The SWMS has to be readily accessible to everyone doing the high risk work, and available for inspection, until that work is finished. After a notifiable incident, keep it for at least 2 years. A copy on a phone or tablet is fine, and if you revise it, keep every version, not just the latest one.

Readily accessible means the crew can read it on site when they need it. If it isn't kept at the site, the Code says it should be somewhere it can be brought to the site quickly. Plenty of crews keep it on their phones with a printed copy in the site box.

Having it on site isn't the end of it. If the work isn't being done the way the SWMS says, stop it straight away, or as soon as it's safe to. Don't restart until the work can be done the SWMS way, or the SWMS has been reviewed and changed to a safe method.

When do you have to review a SWMS?

Review the SWMS whenever its controls change or stop working: the scope changes, the site changes, a near miss shows a gap, or a worker or health and safety rep raises a problem. Consult the crew when you review it, tell everyone what changed, and on a construction project give the principal contractor the new version.

On a trade job, these are the usual triggers:

  • The scope changes, say the roof job now includes new gutters done from a ladder
  • The site changes: the scaffold comes down early, or rain makes the roof slippery
  • A new worker or subbie starts who wasn't there when you went through it
  • Something nearly went wrong
  • A control isn't being followed because it doesn't work on the day

A generic SWMS for work you do every week is a fine starting point. Before it's used on a job, review it for that site and change whatever doesn't fit.

Do SWMS rules change from state to state?

Mostly not. NSW, Queensland, South Australia, Western Australia, Tasmania, the ACT and the Northern Territory all use the model WHS Regulations, so the 18 categories and the SWMS rules line up. Victoria is the main difference: its Occupational Health and Safety Regulations 2017 list 19 categories, and WorkSafe Victoria enforces them. Each regulator publishes its own guidance.

State or territoryRegulator
NSWSafeWork NSW
VictoriaWorkSafe Victoria
QueenslandWorkSafe Queensland
South AustraliaSafeWork SA
Western AustraliaWorkSafe WA
TasmaniaWorkSafe Tasmania
ACTWorkSafe ACT
Northern TerritoryNT WorkSafe

WorkSafe Victoria's SWMS page is a good read wherever you work. It says to name the person responsible for each control, and that a generic or AI-written SWMS has to be reviewed on site, with anything that doesn't apply taken out, before work starts. SafeWork SA put out an updated sample template in June 2026, so if you work in SA and use theirs, get the current one.

Can software write a SWMS for you?

Software can do the typing: the job details, the hazards for the work you tick, controls in the right order and a clean PDF for the builder. It can't walk the site for you. Whoever approves the SWMS is responsible for it, so read every line against the real job, take the crew through it and change what doesn't fit.

That's the test for any SWMS app. Does it start from your actual job and site, or hand you a forty-page generic document? Can the crew read and sign it on their phones? Can you send a new version when the job changes? If you're comparing apps for the rest of the business too, our guide to choosing a tradie app has the questions to ask, and AI for tradies covers what to hand over and what to keep.

If SWMS paperwork is eating your evenings, start a free trial. It's 14 days, no card needed, and you can have the SWMS for your next roof or switchboard job approved and on the crew's phones before you leave the yard.

Questions

No. You need one only for construction work that falls into one of the high risk construction work categories, such as a risk of falling more than 2 metres, work near energised electrical services, or a trench deeper than 1.5 metres. For other work you still have to manage the risks, but a SWMS isn't required.

The business doing the work prepares and approves it. Each worker doing the high risk work should read it and sign on, so there's a record they've been through it. On a construction project, the principal contractor gets a copy before work starts.

You can start from one, but it must be reviewed for the specific site, the work environment and the workers, and changed to fit, before the work starts. A generic SWMS used unchanged on a site it doesn't match won't do the job.

Until the high risk construction work it covers is finished. If there's a notifiable incident, keep it for at least 2 years after. If you revise it, keep every version.

Under the model WHS Regulations, work with a risk of a person falling more than 2 metres is high risk construction work and needs a SWMS. Victoria also sets the fall height at 2 metres.